Modular Prefabricated Construction
In order to guarantee pure material streams, dusty construction sites and last minute changes have to be avoid. The UMAR unit was therefore detailed to the last screw and prefabricated completely in 7 modules at the company Kaufmann Zimmerei und Tischlerei in Reuthe, Austria and pushed to its current position at NEST with the help of 2 cranes within 1 day. On the construction site then only the modules had to be connected (water, electricity, space), which is clearly visible in the video of the construction of the units. The modules can be decoupled extremely quickly and are still on a rail system so that they can be „rolled out“ of the NEST in 5 years without any problems.